ERP North invests in more reliable power supply for over 1000 customers in Ruse region

ERP North has successfully implemented a project for the rehabilitation of a medium-voltage overhead power line “Botrov” Vel 20 kV, which will increase the reliability and quality of power supply in the region.
The project covered a power line with a total length of 14.1 kilometers of overhead line and 415 meters of cable line. The facility provides power supply to a number of substations in the town of Borovo and the village of Batishnitsa in the Ruse region.
Repair work carried out in the first half of April included the replacement of compromised insulators and poles in depreciated technical condition. The investment is part of a comprehensive investment and repair program of the company in order to improve the operational reliability of the network. Its completion will ensure a significantly more stable power supply for the company's more than 1,000 customers, a reduction in the risk of accidents and easier and safer maintenance of the facilities, especially in adverse weather conditions.
With this investment, ERP North continues to implement its strategy to modernize the electricity distribution network and ensure a higher quality of services for its customers.